Patent · US Active

High level central plant optimization

US10175681B2 · kind B2 · utility

53Cited by
78References
20Claims
0Family size

Assignee

Inventors

Key dates

Filing dateFeb 27, 2015
Grant dateJan 8, 2019
Priority date
Expiry dateMay 3, 2036

Classification

  • Technology area (CPC Y)Emerging Cross-Sectional Technologies
  • CPC primaryY04S20/222
  • WIPO fieldControl
  • WIPO sectorInstruments

Abstract

An optimization system for a central plant includes a processing circuit configured to receive load prediction data indicating building energy loads and utility rate data indicating a price of one or more resources consumed by equipment of the central plant to serve the building energy loads. The optimization system includes a high level optimization module configured to generate an objective function that expresses a total monetary cost of operating the central plant over an optimization period as a function of the utility rate data and an amount of the one or more resources consumed by the central plant equipment. The high level optimization module is configured to optimize the objective function over the optimization period subject to load equality constraints and capacity constraints on the central plant equipment to determine an optimal distribution of the building energy loads over multiple groups of the central plant equipment.

Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.