Cluster capacity management for hyper converged infrastructure updates
US11595321B2 · kind B2 · utility
Assignee
Inventors
Key dates
| Filing date | Aug 23, 2021 |
| Grant date | Feb 28, 2023 |
| Priority date | — |
| Expiry date | Aug 23, 2041 |
Classification
- Technology area (CPC H)Electricity
- CPC primaryH04L47/83
- WIPO fieldDigital communication
- WIPO sectorElectrical engineering
Abstract
Disclosed are various implementations of cluster capacity management for infrastructure updates. In some examples, cluster hosts for a cluster can be scheduled for an update. A component of a datacenter level resource scheduler can analyze cluster specific resource usage data to identify a cluster scaling decision for the cluster. The datacenter level resource scheduler transmits an indication that the resource scheduler is successfully invoked. Cluster hosts can then be updated.
Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.