Provisional facility for retaining earth by using ground anchors and guide brackets for stepwise retention during deep excavation, and method for constructing same
US12060689B1 · kind B1 · utility
0Cited by
0References
7Claims
0Family size
Inventor
Key dates
| Filing date | May 25, 2023 |
| Grant date | Aug 13, 2024 |
| Priority date | — |
| Expiry date | May 25, 2043 |
Classification
- Technology area (CPC E)Fixed Constructions
- CPC primaryE02D2600/30
- WIPO fieldCivil engineering
- WIPO sectorOther fields
Abstract
A provisional facility for retaining earth using a guide bracket and a ground anchor for stepwise retention during deep excavation includes multiple thumb piles disposed vertically at predetermined intervals, a wale disposed across the multiple thumb piles, a guide bracket installed at a predetermined position of the wale, and a ground anchor having the other side anchored to a ground while a tensile member is wound around the guide bracket.