Process for the installation of tubes in a steam generator
US4839951A · kind A · utility
Assignee
Inventors
Key dates
| Filing date | Aug 27, 1987 |
| Grant date | Jun 20, 1989 |
| Priority date | — |
| Expiry date | Aug 27, 2007 |
Classification
- Technology area (CPC Y)Emerging Cross-Sectional Technologies
- CPC primaryY10T29/4994
- WIPO fieldThermal processes and apparatus
- WIPO sectorMechanical engineering
Abstract
The process comprises introducing the tubes in the form of horizontal layers (the generator can be positioned horizontally for this purpose), installing anti-vibratory bars on the layers, placing weights on the bars and checking the clearances between the tubes and the bars, so that the tubes falling outside the accepted tolerances can be replaced. This is followed by the installation of the layer of tubes immediately above it. This procedure is repeated until all the layers have been installed. The invention is used in the steam generators of nuclear power stations.
Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.