Patent · US Expired

Method of operating a gas turbine on reformed fuel

US5729967A · kind A · utility

48Cited by
5References
3Claims
0Family size

Assignee

Inventors

Key dates

Filing dateAug 16, 1996
Grant dateMar 24, 1998
Priority date
Expiry dateAug 16, 2016

Classification

  • Technology area (CPC F)Mechanical Engineering; Lighting; Heating
  • CPC primaryF23R3/40
  • WIPO fieldEngines, pumps, turbines
  • WIPO sectorMechanical engineering

Abstract

In a method for the operation of a power station installation which essentially comprises a compressor (4), a combustion unit and a turbine (12), the combustion unit comprising a conditioning stage for at least part of the combustion air and a combustion chamber, a portion (13a) of the compressed air (13) from the compressor (4) is passed through the conditioning stage and there first of all mixed with a quantity of fuel (14a). This mixture then passes into a generator (8), in which at least hydrogen is fractionated, this hydrogen then being used in the combustion chamber. The combustion chamber comprises a start-up burner (1), a catalytic stage (2) and a downstream second combustion stage (3). Both the air/fuel mixture (16a) fractionated in the generator (8) and the further compressor air (13) enter the combustion chamber, in which interdependent combustion occurs between the combustion units acting there, relative to the running up of the installation, for the purpose of minimizing pollutant emissions. (FIG. 1)

Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.