Abstract

An improved well completion system for completing two or more separate production zones in a well bore during a single downhole trip is disclosed. The improved completion system comprises a completion assembly comprising two or more production zone assemblies and a completion tool assembly. Each production zone assembly may comprise an automatic system locating assembly and at least two inverted seal systems for sealing against the tool assembly.