Patent · US Active

Method of operating a steam power plant at low load

US9140143B2 · kind B2 · utility

0Cited by
7References
11Claims
0Family size

Assignee

Inventors

Key dates

Filing dateNov 3, 2012
Grant dateSep 22, 2015
Priority date
Expiry dateNov 3, 2032

Classification

  • Technology area (CPC F)Mechanical Engineering; Lighting; Heating
  • CPC primaryF01K17/06
  • WIPO fieldEngines, pumps, turbines
  • WIPO sectorMechanical engineering

Abstract

A method for operating a steam power plant at low load is suggested comprising the extraction of live steam LS before the last superheater SH3 and/or resuperheated steam before the last resuperheater RSH2 and using the thermal energy of this steam in other heat sinks. Thus, nearly constant steam parameters of the live steam LS are achieved and the overall efficiency of the steam power plant remains at a high level.

Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.