Patent · US Active

Gas turbine power plant with exhaust gas recirculation

US9869246B2 · kind B2 · utility

3Cited by
4References
4Claims
0Family size

Assignee

Inventors

Key dates

Filing dateAug 25, 2014
Grant dateJan 16, 2018
Priority date
Expiry dateAug 3, 2035

Classification

  • Technology area (CPC F)Mechanical Engineering; Lighting; Heating
  • CPC primaryF05D2270/20
  • WIPO fieldEngines, pumps, turbines
  • WIPO sectorMechanical engineering

Abstract

A method for operating a gas turbine power plant, and a gas turbine power plant in which fresh air is delivered to a compressor inlet and is accelerated in the compressor inlet and a recirculated first exhaust gas substream is delivered into a region of the compressor inlet in which the fresh air is accelerated to an extent such that the difference between total pressure and static pressure in the fresh air is greater than or equal to a pressure difference which is required in order to suck a target mass flow of the recirculated first exhaust gas substream into the compressor inlet.

Source: USPTO / EPO open patent data. Objective bibliographic and citation counts.